At 06:12 on Tuesday the first concrete truck backed onto the hoist deck, and by mid-afternoon the twelfth and final floor slab of Building A was poured. The structure is complete — three weeks ahead of the construction program signed in 2025.
The margin came from the winter that never quite arrived and from a decision made back in March: pre-assembling the formwork tables on the ground and flying them between floors in one lift instead of three. That change alone saved roughly two days per floor across the last five floors.
With the frame done, the tower crane switches to facade duty. The first brick-and-aluminum panels arrive from the plant next week and installation starts on the north elevation, working clockwise. If you walk past the site fence on Construction Ave, the change will be visible within days.
Concrete doesn’t care about press releases — either the slab cures on program or it doesn’t. This one did, twelve times in a row.
Elena Marsh, Site Director
The milestone in numbers
- 4,860 m³ of concrete in the frame
- 9 days average per floor cycle
- 0 lost-time incidents
What happens next, in order: facade panels on the north elevation, windows from floor 3 upward, the roof plant deck, then first fix inside. Handover remains on track for Q4 2027. The next update lands in two weeks — or watch the pour timelapse at the sales office, where the show apartment opens September 12.